First Evangelical Free Church Project

EV Free is holding periodic meetings with its neighbors to keep them informed on the project status, and to respond to questions and issues as they arise. Minutes of meetings have been provided to the City by EV Free as a record of items discussed. City representatives are not present at these meeting, and cannot verify the accuracy of the minutes.

Neighbor Meeting Minutes

February 15, 2007

March 27 & 29, 2007

May 10, 2007

June 7, 2007

August 9, 2007

November 1, 2007


Brief Project Description:

Approved project includes a new 20,000 square foot multi-purpose building, a 16,000 square foot administrative building and a three-level parking structure (two stories plus roof parking) at 2801 N. Brea Blvd. An Initial Study and Mitigated Negative Declaration has been prepared to evaluate the potential environmental impacts of the project.

Status as of 2/6/2007:

Minutes for the Community Meeting held January 17, 2007 have been posted here.

Status as of 1/18/2007:

Parking structure construction expected to begin in late January 2007, and to complete in November 2007.

Grading permit issued and grading is nearing completion.

Landscape plans approved by RDRC October 26, 2006.

Project approved by City Council July 18, 2006.

Status as of 10/17/06:

Project approved by Planning Commission on 1/25/06

Project approved by City Council on 7/18/06

Project scheduled for review by Redevelopment Design Review Committee (landscape plans) on 10/26/06

Status as of 7/18/06: Documents added

Building G - Elevation Option #2

Building H - Elevation Option #2

Parking Structure, East and West Elevations

Parking Structure, North and South Elevations

Parking Structure Striping Plan, Level 1

Parking Structure Striping Plan, Level 2

Parking Structure Striping Plan, Level 3

Parking Structure Traffic Flow Diagram

Parking Operations Model

Status as of 7/12/06: Documents added

Summary of Applicant changes since May 20 City Council Meeting Further changes, July 14th, included (61 KB PDF)

Photo simulations of parking structure viewed from residential lots

Lot 1 view with 86 foot setback to "new" elevation, no landscaping buffer

Lot 1 view with 86 foot setback to "new" elevation, with landscaping buffer

Lot 2 view with 86 foot setback to "new" elevation, with landscaping buffer

Lot 2 view with 86 foot setback to "new" elevation, no landscaping buffer

Slide Show Presentation at 7/10/06 Community Meeting

Status as of 7/11/06: Documents added

Traffic Report posted: Entire Report (9.24MB) OR Report in sections: Part 1 (3.96 MB), Part 2 (5.43 MB)

Status as of 6/19/06: Document added

Slide Show Presentation at 6/19/06 Community Meeting

Status as of 6/1/06:

Project, as proposed, was denied without prejudice by the City Council at a public hearing held on May 2, 2006. The applicant has proposed design modifications. At their June 6, 2006 meeting, the City Council may consider a motion to agendize the project. If the motion is approved, a public hearing will be set, likely for the June 20, 2006 City Council meeting.

Status as of 1/18/06:

Scheduled for Planning Commission public hearing on January 25, 7:00 p.m.

Approval recommended by Redevelopment Design Review Committee on January 12, 2006


Status as of 1/4/06: Documents posted


For more information, contact:

Project Applicant:
First Evangelical Free Church of Fullerton
2801 N. Brea Blvd.
Fullerton, Ca 92835
Jim Clark, Director of Operations (714) 529-5544

Contact Information for Construction Issues:

Matt Prince, EV Free Director of Operations: (714) 529-5544 ext. 409

Gary Johnson, EV Free representative: (714) 525-9897 or (714) 306-7633 (cell)

City:
Joan Wolff (714)738-6837

Home | Contact Us | FAQs | Service Request | Site Map | Disclaimer & Privacy Policy | Translate: More Languages
Copyright © 2000 - 2008 City of Fullerton. Community Development, 303 W. Commonwealth, Fullerton, CA 92832. (714) 738-6540